Monday, 26 October 2009 - 18:16 |
US Refinery Status: Hovensa Shuts St. Croix FCCU -2- |
Chevron Pascagoula, 330.0 Pre-commercial heavy oil 2010
Miss. conversion project delayed
from 2008 to 2010 due to
economic factors.
Conoco Sweeny, TX 247.0 Six weeks of turnaround work Oct 30
starts Sept. 14 at Units 14,
9, 38 and 27, which is an
FCCU.
Tail gas incinerator shut during Nov. 1
fall turnaround Sept. 30
Exxon Baytown 572.5 FCCU No. 3 shut Sep 15. for
TX planned maintenance.
Flint Corpus 288.1 $250 mln project for new Spr
Hills Christi, TX diesel desulfurization, 2010
sulfur recovery unit to begin
in Fall 2008. Construction
to last 18 months.
Marathon Garyville 245.0 Project to increase crude oil 4Q
LA refining capacity by 180,000- 2009
b/d 85% complete, as of end
April. New units expected
start up in 4Q 2009.
Motiva Port Arthur 285.0 Expansion project to increase 1Q
TX throughput capacity by 325,000 2012
b/d, to 610,000-b/d, slowed.
Completion now seen 1Q
2012, from 2010.
Shell Deer Park, 340.0 Hydroprocessing unit, cata- Oct 24
lytic cracker unit and alky-
lation shut between Oct 1 and
Oct 24 for fall turnaround
maintenance.
Total Port Arthur 232.0 Shut unit 805 for Oct. 8
maintenance on Oct. 5.
Shut unit 810 for work Sept.22
Unit 822 restarted Sept. 29
Restarted 837 Oct. 1
Valero Corpus 340.0 Coker unit shutdown for econo- n/a
Christi, TX mic reasons and planned work;
delayed to June 19 from June
12. The 20,000-b/d unit will
remain off line through July
but could restart at any time
if margins improve.
20,000-b/d FCCU in East n/a
Plant shut; West Plant
50,000-b/d FCCU at reduced
rates since mid-Dec for
economic reasons.
Valero Norco, LA 250.0 Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Turnaround at coker unit 1Q
delayed until 1Q 2010
from 4Q 2009.
The coker will operate at
50% of capacity when
restarted due to poor
economics.
Valero Port Arthur 325.0 77,000-b/d FCCU at reduced n/a
TX rates since mid-Dec for
economic reasons.
Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a
rates since mid-Dec for
economic reasons.
Valero Three Rivers 95.0 Plant-wide 24-day turnaround Oct. 2
Order free Annual Report for BP plc Visit http://djnewswires.ar.wilink.com/?link=BP or call 1-888-301-0513 Order free Annual Report for ConocoPhillips Visit http://djnewswires.ar.wilink.com/?link=COP or call 1-888-301-0513 Order free Annual Report for Chevron Corporation Visit http://djnewswires.ar.wilink.com/?link=CVX or call 1-888-301-0513 Order free Annual Report for Marathon Oil Corporation Visit http://djnewswires.ar.wilink.com/?link=MRO or call 1-888-301-0513 Order free Annual Report for Exxon Mobil Corporation Visit http://djnewswires.ar.wilink.com/?link=XOM or call 1-888-301-0513 (END) Dow Jones Newswires October 26, 2009 11:16 ET (15:16 GMT) Copyright (c) 2009 Dow Jones & Company, Inc. |